Project Duration
Stipulated Date of Commencement
September 24 2013
Stipulated Date of Completion /
Likely Date of Completion December 23 2013
Likely Date of Completion December 23 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 499,875.00
Awarded for
₹ 494,875.00
Project highlights
Poviding 315 KVA transformer
Contractors
M/s. Swaki Electrical Pvt. Ltd.
Consultants
In-house (GSIDC)