Project Duration
Stipulated Date of Commencement
October 08 2007
Stipulated Date of Completion /
Likely Date of Completion November 07 2007
Likely Date of Completion November 07 2007
Status
100%
Completed
Cost (₹)
Estimated at
₹ 17,395,782.00
Awarded for
₹ 19,798,057.87
Contractors
M/s. ETA General Pvt. Ltd.
Consultants
M/s. Effective Architectural Services