Project Duration
Stipulated Date of Commencement
November 15 2018
Stipulated Date of Completion /
Likely Date of Completion August 15 2019
Likely Date of Completion August 15 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 12,968,423.00
Awarded for
₹ 13,587,959.00
Project highlights
Roofing work, Tilling work Painting , Repairing of window & doors,plumbing works, electrical works, etc.
Contractors
M/s. Sri Sri Akruthi Projects Pvt. Ltd
Consultants
M/s Bhaskar Wagle & Associates
See Similar Projects
Repairs/Upgradation and Maintenance of Govt. schools in the state of Goa – Civil, Plumbing and Electrical works -Bicholim Taluka-Package G (G.P.S. Sal, G.P.S. Bhamai Pale, G.P.S. Lower Harvalem)
View Project
Repairs/Upgradation and Maintenance of Government Schools in the state of Goa-Mormugao Taluka-Package C (GPS Cansaulim, GPS Podxiro, GPS Chicalim, GPMS Cortalim)
View Project
Repairs/Upgradation & Maintenance of Govt. Schools in the State of Goa- (Canacona taluka) – Package D (GPS Chavdi, GPS C…., GPS Desaiwada, GPS Kindlebag, GPS Panyefond)
View Project