Project Duration
Stipulated Date of Commencement
February 01 2017
Stipulated Date of Completion /
Likely Date of Completion January 01 2018
Likely Date of Completion January 01 2018
Status
100%
Completed
Cost (₹)
Estimated at
₹ 45,782,655.00
Awarded for
₹ 47,540,516.74
Project highlights
Repair/Upgrdation works of schools which includes roofing ,tiling,dadoes,painting etc.
Contractors
M/s.K G Thomas
Consultants
M/s.Manoj Amshekar
See Similar Projects
Reconstruction of Government High School at Ambedem, Nagargao in Sattari taluka – Civil, plumbing & electrical works.
View Project
Repairs/Upgradation and Maintenance of Government Primary Schools in the State of Goa Dharbandora Taluka – Package V (GPS Dhadewada, GPS Kodli Tisk, GPS Saton, GPS Navawada, GPS Pratapnagar, GPS Shigao)
View Project
Repairs /Upgradation & Maintenance of Government schools in the state of Goa -Civil,Plumbing & Electrical works – Package IV-D
View Project





