Project Duration
Stipulated Date of Commencement
December 19 2018
Stipulated Date of Completion /
Likely Date of Completion June 19 2019
Likely Date of Completion June 19 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,824,596.00
Awarded for
₹ 3,063,396.61
Project highlights
Repairs/Upgradation and maintenance of Government schools in the state of Goa – Sattari Taluka
Contractors
M/s. Manup Infrastructures
Consultants
M/s. Bhaskar Wagle and Associates