Project Duration
Stipulated Date of Commencement
January 05 2008
Stipulated Date of Completion /
Likely Date of Completion July 29 2008
Likely Date of Completion July 29 2008
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,834,858.00
Awarded for
₹ 2,298,500.00
Contractors
M/s. Vrindavan Agricultural Services
Consultants
M/s. Vijaykumar Sawant Associates