Project Duration
Stipulated Date of Commencement
December 16 2015
Stipulated Date of Completion /
Likely Date of Completion February 15 2016
Likely Date of Completion February 15 2016
Status
100%
Completed
Cost (₹)
Estimated at
₹ 6,335,171.00
Awarded for
₹ 5,277,777.00
Project highlights
Acoustic works in Auditorium
Contractors
M/s. Harshada Trading Company
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd