Project Duration
Stipulated Date of Commencement December 16 2015
Stipulated Date of Completion /
Likely Date of Completion
February 15 2016
Status
100%
Completed
Cost (₹)
Estimated at ₹ 6,335,171.00
Awarded for ₹ 5,277,777.00

Project highlights

Acoustic works in Auditorium

 
Gallery Image
Contractors
M/s. Harshada Trading Company
Gallery Image
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd
 
Similar Projects

See Similar Projects

Similar Project

Supply & Installation of Lead Doors & Lead Glass

View Project
Similar Project

Construction of New Premises for Community Health Centre at Tuem, Pernem Goa and Major Civil works sanctioned under NRHM – ROP 2012-13.: Phase I: Repair and upgradation works of existing community health centre under NRHM

View Project
Similar Project

Construction of Sewage Treatment Plant including sewage network at Institute of Psychiatry & Human Behaviour complex at Bambolim, Goa -Construction of building and sewage pipeline work

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.