Project Duration
Stipulated Date of Commencement
April 01 2018
Stipulated Date of Completion /
Likely Date of Completion April 30 2021
Likely Date of Completion April 30 2021
Status
100%
Completed
Cost (₹)
Estimated at
₹ 19,972,974.00
Awarded for
₹ 23,053,800.00
Project highlights
0.4 MLD STP & RO Plant
Contractors
M/s. Brisanzia Technologies Pvt. Ltd.
Consultants
M/s. KICONS Limited
See Similar Projects
Design, supply, erection, testing and commissioning of 5 Nos. pre-fabricated Modular Operation Theatres along with centralised medical gas pipe system within the 5 No. OTs at Goa Medical College & Hospital, Bambolim, Goa