Project Duration
Stipulated Date of Commencement
March 07 2021
Stipulated Date of Completion /
Likely Date of Completion July 06 2021
Likely Date of Completion July 06 2021
Status
100%
Completed
Cost (₹)
Estimated at
₹ 26,715,288.00
Awarded for
₹ 24,986,955.00
Project highlights
Project consist of providing kitchen ware items, carpentary furnitures, electrical goods lift and other miscellaneous items.
Contractors
M/s.Creative Design & Products
Consultants
M/s. Ulysis