Project Duration
Stipulated Date of Commencement
February 26 2014
Stipulated Date of Completion /
Likely Date of Completion August 25 2015
Likely Date of Completion August 25 2015
Status
100%
Completed
Cost (₹)
Estimated at
₹ 377,910,694.72
Awarded for
₹ 415,663,311.00
Project highlights
Project consist of construction of school building, boys hostel and girls hostels for tribal community with capacity of 500 students.
Contractors
M/s. Harsh Construction Pvt. Ltd.
Consultants
M/s. Ulysis