Project Duration
Stipulated Date of Commencement
September 04 2019
Stipulated Date of Completion /
Likely Date of Completion March 13 2020
Likely Date of Completion March 13 2020
Status
100%
Completed
Cost (₹)
Estimated at
₹ 5,228,121.00
Awarded for
₹ 6,461,335.69
Project highlights
Repairs/Upgradation and Maintenance of Govt. schools in the state of Goa
Contractors
M/s. Prashant Rangrao Desai
Consultants
M/s. Nitin Arolkar