Project Duration
Stipulated Date of Commencement
February 22 2014
Stipulated Date of Completion /
Likely Date of Completion May 21 2014
Likely Date of Completion May 21 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 50,941,974.00
Awarded for
₹ 55,959,830.20
Project highlights
Construction of new two lane bridge by demolishing old bridge which was in depilated condition.
Contractors
M/s. M. Venkata Rao Infra Projects Pvt. Ltd.
Consultants
M/s. Madhav Kamat & Associates