Project Duration
Stipulated Date of Commencement April 26 2007
Stipulated Date of Completion /
Likely Date of Completion
October 25 2007
Status
100%
Completed
Cost (₹)
Estimated at ₹ 27,644,386.00
Awarded for ₹ 34,552,373.00
 
Gallery Image
Contractors
M/s. Kirloskar Constructions & Engineers Limited
Gallery Image
Consultants
M/s. Construma Consultancy Pvt. Ltd.
 

Sub Works

This project involved 2 sub works. The details of the same available below

1

Construction of Jetty at Brittona – Additional works.

100% completed
 
Project Duration
Stipulated Date of Commencement July 16 2010
Stipulated Date of Completion /
Likely Date of Completion
October 15 2010
Status
100%
Completed
Cost (₹)
Estimated at ₹ 1,985,905.00
Awarded for ₹ 2,183,970.00
 
Contractors
Contractors
M/s. Deshpande Constructions
Consultants
Consultants
M/s. Vijaykumar Sawant Associates
2

Construction of Jetty at Brittona – Additional electrical works

100% completed
 
Project Duration
Stipulated Date of Commencement April 06 2010
Stipulated Date of Completion /
Likely Date of Completion
June 05 2010
Status
100%
Completed
Cost (₹)
Estimated at ₹ 609,064.00
Awarded for ₹ 651,172.00
 
Contractors
Contractors
M/s. Oman Enterprises
Consultants
Consultants
In-house (GSIDC)
Similar Projects

See Similar Projects

Similar Project

Design and construction of bridge at Satrem – Construction of approach roads.

View Project
Similar Project

Construction of Pedestrian Arch Bridge connecting Mandovi River Promenade and DB Road, over St. Inez Creek near ESG Building at Panaji

View Project
Similar Project

Improvement and upgradation of existing road from Azad Bhavan to Socorro Panchayat in Bardez Taluka.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.