Project Duration
Stipulated Date of Commencement
October 28 2014
Stipulated Date of Completion /
Likely Date of Completion November 27 2014
Likely Date of Completion November 27 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 45,817,308.00
Awarded for
₹ 49,506,270.40
Project highlights
Conversion of electrical overhead lines to underground cables.
Contractors
M/s. Nanu Engineers Pvt. Ltd.,
Consultants
M/s. Nitin Arolkar