Project Duration
Stipulated Date of Commencement
January 25 2007
Stipulated Date of Completion /
Likely Date of Completion March 24 2008
Likely Date of Completion March 24 2008
Status
100%
Completed
Cost (₹)
Estimated at
₹ 43,027,157.00
Awarded for
₹ 49,303,872.49
Contractors
M/s. BGM Consortium Pvt. Ltd.
Consultants
M/s. Effective Architectural Services
Sub Works
This project involved 1 sub works. The details of the same available below
1
Lifts / Elevator work.
100% completed
Project Duration
Stipulated Date of Commencement
February 19 2010
Stipulated Date of Completion /
Likely Date of Completion June 18 2010
Likely Date of Completion June 18 2010
Status
100%
Completed
Cost (₹)
Estimated at
₹ 691,420.00
Awarded for
₹ 792,560.00
Contractors
M/s. Thyssenkrupp Elevators (I) Pvt. Ltd.
Consultants
M/s. Effective Architectural Services
See Similar Projects
Repairs/Upgradation & maintenance of Government SchoolS in State of Goa -Quepem Taluka-Package C (GPS Curchorem Main)
View Project
Repairs/Upgradation & maintenance of Government schools in the state of Goa – Tiswadi taluka – Package-I (GPS Dhulapi, GPS Mangoda, GPS Gawant, GPS Akhada)
View Project
Reconstruction of GHS at Taramata bhile Surla in Bicholim Taluka
View Project