Project Duration
Stipulated Date of Commencement
January 31 2019
Stipulated Date of Completion /
Likely Date of Completion October 09 2019
Likely Date of Completion October 09 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 12,953,520.88
Awarded for
₹ 14,737,217.90
Project highlights
Repairs/ Upgradation & Maintenance of schools
Contractors
M/s. Hari Krishna Constructions
Consultants
M/s. Datta kare associates