Project Duration
Stipulated Date of Commencement
September 26 2019
Stipulated Date of Completion /
Likely Date of Completion February 29 2024
Likely Date of Completion February 29 2024
Status
100%
Completed
Cost (₹)
Estimated at
₹ 31,074,285.00
Awarded for
₹ 27,291,564.00
Project highlights
The scope of work includes false ceiling, paritions, panelling, granite cladding, tac tiles, signages, aluminium louvers, etc.
Contractors
M/s. Virender Kumar & Co.
Consultants
M/s. M:OFA Studios Pvt. Ltd.
See Similar Projects
Repairs/Upgradation and Maintenance of Government Primary Schools in the State of Goa Dharbandora Taluka – Package IV (GPS Hauliwada, GPS Kalsai, GPS Camarconda, GPS Matoje, GPS Panaswada)
View Project
Supply, Installation, Testing & Commissioning of CCTV & PA System
View Project
Repairs/Upgradation & Maintenance of Government Schools In the State of Goa – Ponda Taluka: Package-E (GPS Marvel Curti, GPS Deulwada Borim, GPS Mhalshe Curti, GPS Nagar, GPS Tambdi Curti and GPS Copperwada Curti ).
View Project