Project Duration
Stipulated Date of Commencement September 26 2019
Stipulated Date of Completion /
Likely Date of Completion
February 29 2024
Status
100%
Completed
Cost (₹)
Estimated at ₹ 31,074,285.00
Awarded for ₹ 27,291,564.00

Project highlights

The scope of work includes false ceiling, paritions, panelling, granite cladding, tac tiles, signages, aluminium louvers, etc.

 
Gallery Image
Contractors
M/s. Virender Kumar & Co.
Gallery Image
Consultants
M/s. M:OFA Studios Pvt. Ltd.
 
Similar Projects

See Similar Projects

Similar Project

Repairs/Upgradation and Maintenance of Government Primary Schools in the State of Goa Dharbandora Taluka – Package IV (GPS Hauliwada, GPS Kalsai, GPS Camarconda, GPS Matoje, GPS Panaswada)

View Project
Similar Project

Supply, Installation, Testing & Commissioning of CCTV & PA System

View Project
Similar Project

Repairs/Upgradation & Maintenance of Government Schools In the State of Goa – Ponda Taluka: Package-E (GPS Marvel Curti, GPS Deulwada Borim, GPS Mhalshe Curti, GPS Nagar, GPS Tambdi Curti and GPS Copperwada Curti ).

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.