Project Duration
Stipulated Date of Commencement
January 03 2019
Stipulated Date of Completion /
Likely Date of Completion August 31 2019
Likely Date of Completion August 31 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 47,193,574.50
Awarded for
₹ 62,030,298.77
Project highlights
The project consist of supply and erection of new medical gas line distribution system such as Oxygen Manifold system, Air compressors, Vaccumm Plant etc
Contractors
M/s. Prenit World LLP
Consultants
M/s. KICONS Limited