Project Duration
Stipulated Date of Commencement
December 18 2007
Stipulated Date of Completion /
Likely Date of Completion March 01 2008
Likely Date of Completion March 01 2008
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,667,482.00
Awarded for
₹ 2,508,525.00
Contractors
M/s. Ohm Engineers & Electricals Pvt. Ltd.