Project Duration
Stipulated Date of Commencement
December 23 2005
Stipulated Date of Completion /
Likely Date of Completion February 10 2006
Likely Date of Completion February 10 2006
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,260,953.00
Awarded for
₹ 1,391,854.80
Project highlights
Repairing of existing road by cleaning, levelling, filling of pot holes, constructing S.W.D., catch pits, inspection chambers, precast concrete pipes, etc.
Contractors
M/s. Assmas Constructions Pvt. Ltd.
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd
See Similar Projects
Maintenance work of Goa Medical College & Hospital and Goa Dental College at Bambolim, Goa. S.H.: Supply, Installation, Testing & Commissioning of 30KVA online UPS systems for ICU 123 and Modular OT 5 at Goa Medical College.
View Project
Civil, Plumbing & Electrical works – Phase I.
View Project
Maintenance of hospitals CHC’s, PHC’s, RMD’s under Directorate of Health services S.H Maintenance of Split & window Air conditioning units at various location in the state of Goa for a period of 3 years.
View Project