Project Duration
Stipulated Date of Commencement January 05 2007
Stipulated Date of Completion /
Likely Date of Completion
May 04 2007
Status
100%
Completed
Cost (₹)
Estimated at ₹ 24,264,548.25
Awarded for ₹ 22,590,380.00
 
Gallery Image
Contractors
M/s. Concept Creators
Gallery Image
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd
 