Project Duration
Stipulated Date of Commencement
October 04 2007
Stipulated Date of Completion /
Likely Date of Completion January 03 2008
Likely Date of Completion January 03 2008
Status
100%
Completed
Cost (₹)
Estimated at
₹ 8,314,729.00
Awarded for
₹ 8,015,705.00
Contractors
M/s. Paradyne Infotech Limited
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.