Project Duration
Stipulated Date of Commencement
August 01 2019
Stipulated Date of Completion /
Likely Date of Completion August 10 2019
Likely Date of Completion August 10 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 10,528,091.00
Awarded for
₹ 12,883,641.47
Project highlights
Sewage treatment plant
Contractors
M/s. Raveena Watertech,
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd.