Project Duration
Stipulated Date of Commencement
October 26 2020
Stipulated Date of Completion /
Likely Date of Completion December 31 2023
Likely Date of Completion December 31 2023
Status
100%
Completed
Cost (₹)
Estimated at
₹ 6,851,435.00
Awarded for
₹ 4,998,675.00
Project highlights
Maintenance Work
Contractors
M/s. Vigneshwar Air Conditioning Pvt. Ltd
Consultants
In-house (GSIDC)
See Similar Projects
Upgradation of Hospital facilities at Goa Medical College, Bambolim, Hospicio Hospital at Margao and RMD at Thane & Keri. SH- Upgradation of Ward Nos. 120, 123, 124, staff rest rooms and other miscellaneous works at Goa Medical College and Hospital at Bambolim, Goa-Extension of Ward 125 for Cardiology Department at Goa Medical College, Bambolim-Goa.