Project Duration
Stipulated Date of Commencement
March 17 2009
Stipulated Date of Completion /
Likely Date of Completion March 16 2010
Likely Date of Completion March 16 2010
Status
100%
Completed
Cost (₹)
Estimated at
₹ 33,782,875.00
Awarded for
₹ 34,574,345.00
Project highlights
Repairs works
Contractors
M/s. Kanaka Infratech Ltd.
Consultants
M/s. FP INDIA PROJECT MANAGEMENT CONSULTANCY SERVCIES PVT. LTD