Project Duration
Stipulated Date of Commencement
September 08 2004
Stipulated Date of Completion /
Likely Date of Completion October 07 2004
Likely Date of Completion October 07 2004
Status
100%
Completed
Cost (₹)
Estimated at
₹ 350,184.40
Awarded for
₹ 366,922.00
Contractors
M/s. Sandesh C. Naik
Consultants
M/s. Vijaykumar Sawant Associates