Project Duration
Stipulated Date of Commencement October 12 2018
Stipulated Date of Completion /
Likely Date of Completion
September 02 2019
Status
100%
Completed
Cost (₹)
Estimated at ₹ 2,127,060.00
Awarded for ₹ 1,823,808.00

Project highlights

SITC of 30KVA online UPS systems for ICU 123 and Modular OT 5 at Goa Medical College.

 
Gallery Image
Contractors
M/s. Power Resources,
Gallery Image
Consultants
In-house (GSIDC)
 
Similar Projects

See Similar Projects

Similar Project

Construction of Institute of Nursing Education Complex at Bambolim, Goa – Civil, Plumbing & Internal Electrical works

View Project
Similar Project

Extension of R.M.O Hostel at Goa Medical College and Hospital, Bambolim, Goa S.H.: Interior, Furniture works

View Project
Similar Project

Maintenance work of Goa Medical College & Hospital and Goa Dental College at Bambolim, Goa. S.H.: Supply, Installation, Testing & Commissioning of Cold storage unit for Microbiology Department at Goa Medical College.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.