Project Duration
Stipulated Date of Commencement
August 18 2014
Stipulated Date of Completion /
Likely Date of Completion October 17 2014
Likely Date of Completion October 17 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,833,300.00
Awarded for
₹ 1,870,000.00
Contractors
M/S. MEDEX INDIA (P) LTD;
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd.