Project Duration
Stipulated Date of Commencement
March 01 2014
Stipulated Date of Completion /
Likely Date of Completion May 01 2014
Likely Date of Completion May 01 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 3,857,508.00
Awarded for
₹ 4,404,197.00
Project highlights
Construction of water storage tank for fire safety purpose
Contractors
M/s. K. V. Gaonkar,
Consultants
M/s. Frishmann Prabhu (I) Pvt. Ltd.