Project Duration
Stipulated Date of Commencement January 21 2019
Stipulated Date of Completion /
Likely Date of Completion
April 20 2019
Status
100%
Completed
Cost (₹)
Estimated at ₹ 8,283,986.50
Awarded for ₹ 7,900,444.46

Project highlights

Power supply for High Court Complex

 
Gallery Image
Contractors
M/s. Consistent Engineers
Gallery Image
Consultants
 
Similar Projects

See Similar Projects

Similar Project

Internal, external and special lighting fixtures (Part A – Supply of internal light fixtures / fans)

View Project
Similar Project

Painting Landscaping and other ancillary works along DB Road for IFFI 2017

View Project
Similar Project

Interior & Acoustic Work

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.