Project Duration
Stipulated Date of Commencement
November 06 2014
Stipulated Date of Completion /
Likely Date of Completion May 05 2014
Likely Date of Completion May 05 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,83,63,862
Awarded for
₹ 1,75,60,152.33
Project highlights
repairs and painting of roads and kerb stones around Panaji for IFFI 2014.
Contractors
M/s. Abhiyant Realty
Consultants
M/s. Nitin Arolkar