Project Duration
Stipulated Date of Commencement
February 22 2014
Stipulated Date of Completion /
Likely Date of Completion March 21 2014
Likely Date of Completion March 21 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 613,577.00
Awarded for
₹ 638,500.00
Contractors
M/s. RICOH India Ltd.,
Consultants
In-house (GSIDC)