Project Duration
Stipulated Date of Commencement
June 10 2018
Stipulated Date of Completion /
Likely Date of Completion October 09 2018
Likely Date of Completion October 09 2018
Status
100%
Completed
Cost (₹)
Estimated at
₹ 14,961,876.87
Awarded for
₹ 13,580,518.24
Project highlights
The project involved providing modular as well as medical furnitures for new hospital and hostel at Mandur
Contractors
M/s. Deshpande Constructions
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd