Project Duration
Stipulated Date of Commencement
October 26 2006
Stipulated Date of Completion /
Likely Date of Completion February 25 2007
Likely Date of Completion February 25 2007
Status
100%
Completed
Cost (₹)
Estimated at
₹ 15,119,623.00
Awarded for
₹ 11,376,000.00
Contractors
M/s. BOC India Limited
Consultants
M/s. FP INDIA PROJECT MANAGEMENT CONSULTANCY SERVCIES PVT. LTD