Project Duration
Stipulated Date of Commencement
December 14 2019
Stipulated Date of Completion /
Likely Date of Completion December 13 2020
Likely Date of Completion December 13 2020
Status
100%
Completed
Cost (₹)
Estimated at
₹ 57,329,858.55
Awarded for
₹ 43,924,239.85
Contractors
M/S.VIPIN SHAH & ASSOCIATES.
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd.
See Similar Projects
Remodelling of existing Sewage Treatment Plant for GMC, Bambolim, Goa (C-Tech).
View Project
External Electrical works
View Project
Minor Maintenance / Renovation works at Hospitals, Health Centres and Institutions under Directorate of Health Services, in the State of Goa – Roofing Works for District Hospital, Mapusa-Goa
View Project