Project Duration
Stipulated Date of Commencement December 28 2010
Stipulated Date of Completion /
Likely Date of Completion
September 27 2011
Status
100%
Completed
Cost (₹)
Estimated at ₹ 1,04,70,991.00
Awarded for ₹ 9,545,205.95
 
Gallery Image
Contractors
M/s. Sunshine Electric Co. Pvt. Ltd.
Gallery Image
Consultants
M/s. Effective Architectural Services
 
Similar Projects

See Similar Projects

Similar Project

Additional infrastructure works for GMC & H – Demolition & construction of Hospital and Hostel at Mandur, Goa – S.H. – Furniture and interior works

View Project
Similar Project

Design, supply, erection, testing and commissioning of 5 Nos. pre-fabricated Modular Operation Theatres along with centralised medical gas pipe system within the 5 No. OTs at Goa Medical College & Hospital, Bambolim, Goa

View Project
Similar Project

Fire Fighting Works.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.