Project Duration
Stipulated Date of Commencement
February 07 2015
Stipulated Date of Completion /
Likely Date of Completion February 06 2016
Likely Date of Completion February 06 2016
Status
100%
Completed
Cost (₹)
Estimated at
₹ 73,480,851.00
Awarded for
₹ 97,176,913.14
Project highlights
Civil, Plumbing, Electrical, Lift & Fire – Fighting works.
1. The total bed capacity is 42.
2.The ground floor of the building shall have Casualty, 8 OPD’s & other rooms.
3.The first floor of the building shall have Operation theatre, Recovery room, etc.
Contractors
M/s. shilpi Constructions
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd.
See Similar Projects
Upgradation and extension of existing Cottage Hospital at Chicalim, Goa – (120 Bedded Cottage Hospital, Chicalim) Civil, Plumbing, Electrical, Firefighting, HVAC, Lifts and Land development works
View Project
Supply, Testing and Commissioning of Ventilators with Humidifiers
View Project
Construction of Girls Hostel at Goa Medical College & Hospital at Bambolim, Goa – Interior and Furniture Works
View Project