Project Duration
Stipulated Date of Commencement September 19 2018
Stipulated Date of Completion /
Likely Date of Completion
September 24 2018
Status
100%
Completed
Cost (₹)
Estimated at ₹ 135,591.00
Awarded for ₹ 133,236.00

Project highlights

The scope of work includes HT tapping work for obtaining electricity connection to PHC Navelim.

 
Gallery Image
Contractors
M/s. Voltas Engineering Pvt. Ltd.
Gallery Image
Consultants
In-house (GSIDC)
 
Similar Projects

See Similar Projects

Similar Project

Major Maintenance Work of Goa Medical College and Hospital at Bambolim, Goa Major Maintenance Work of Goa Medical College and Hospital at Bambolim, Goa. SH : Maintenance of Split, Window Type, Mega split, Multi split and Tower type Air Conditioners installed in GMC Complex, Bambolim (2020-2023)

View Project
Similar Project

Medical gas and Vacuum System work

View Project
Similar Project

Supply Installation Testing & Commissioning of Bio Medical Equipment (Part II) Colour doppler & Ultra Sonography.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.