Project Duration
Stipulated Date of Commencement
February 27 2004
Stipulated Date of Completion /
Likely Date of Completion December 25 2004
Likely Date of Completion December 25 2004
Status
100%
Completed
Cost (₹)
Estimated at
₹ 39.85 lakh
Awarded for
₹ 39.81 lakh
Contractors
M/s. Sandesh C. Naik and M/s. C. V. Naik & Son
Consultants
M/s. Vijaykumar Sawant Associates
See Similar Projects
S.H. Carriage of Water
View Project
Upgradation of Hospital facilities at Goa Medical College, Bambolim, Hospicio Hospital at Margao and RMD at Thane & Keri. SH- Upgradation of Ward Nos. 120, 123, 124, staff rest rooms and other miscellaneous works at Goa Medical College and Hospital at Bambolim, Goa -Extension of Ward 125 for Cardiology Department at Goa Medical College, Bambolim-Goa – Supply, Installation in specified location, Testing and Commissioning of Advanced Non Invasive Ventilator with Humidifier including Compressor
View Project
Additions and Alterations to ground floor area of Foyer Block at GMC, Complex, Bambolim, Goa.
View Project