Project Duration
Stipulated Date of Commencement
June 19 2017
Stipulated Date of Completion /
Likely Date of Completion June 18 2017
Likely Date of Completion June 18 2017
Status
100%
Completed
Cost (₹)
Estimated at
₹ 9,115,875.00
Awarded for
₹ 8,619,018.75
Project highlights
Carriage of water from Altinho to Bambolim
Contractors
M/s. Pedro Gomes
Consultants
In-house (GSIDC)