Project Duration
Stipulated Date of Commencement
May 18 2012
Stipulated Date of Completion /
Likely Date of Completion August 17 2013
Likely Date of Completion August 17 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 203,769,219.16
Awarded for
₹ 218,995,475.01
Project highlights
Civil, Plumbing & Electrical work of new building & Renovation of old building
Contractors
M/s. M. Venkata Rao Infra Projects Pvt. Ltd.
Consultants
M/s. Banaji & Associates