Project Duration
Stipulated Date of Commencement May 18 2012
Stipulated Date of Completion /
Likely Date of Completion
August 17 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 203,769,219.16
Awarded for ₹ 218,995,475.01

Project highlights

Civil, Plumbing & Electrical work of new building & Renovation of old building

 
Gallery Image
Contractors
M/s. M. Venkata Rao Infra Projects Pvt. Ltd.
Gallery Image
Consultants
M/s. Banaji & Associates
 
Similar Projects

See Similar Projects

Similar Project

Construction of Government Primary school at Vasantnagar, Sankhali in Bicholim Taluka.

View Project
Similar Project

Repairs /Upgradation & Maintenance of Government schools in the state of Goa -Civil,Plumbing & Electrical works – Package IV-B

View Project
Similar Project

Repairs /Upgradation & Maintenance of Government schools in the state of Goa -Civil,Plumbing & Electrical works – Package IV-C

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.