Project Duration
Stipulated Date of Commencement
February 08 2019
Stipulated Date of Completion /
Likely Date of Completion November 21 2019
Likely Date of Completion November 21 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 9,543,158.00
Awarded for
₹ 10,992,111.60
Project highlights
Repair/Upgrdation works of schools which includes roofing , tiling,dadoes,painting etc.
Contractors
M/s.Sushant Khedekar
Consultants
M/s.Bhaskar Wagle & Associates