Project Duration
Stipulated Date of Commencement
August 03 2018
Stipulated Date of Completion /
Likely Date of Completion July 01 2019
Likely Date of Completion July 01 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 8,252,849.00
Awarded for
₹ 8,610,526.17
Project highlights
Repairs/ Upgradation & Maintenance of schools
Contractors
M/s.Bharti Infrastructure Developers
Consultants
M/s.Nitin Arolkar
See Similar Projects
Repairs/Upgradation & Maintenance of Govt. Schools in the state of Goa – Package L (Sattari Taluka) – (GPS Barazan, GPS Khadki, GPS Velge, GPS Khotode)