Project Duration
Stipulated Date of Commencement
October 07 2019
Stipulated Date of Completion /
Likely Date of Completion June 16 2020
Likely Date of Completion June 16 2020
Status
100%
Completed
Cost (₹)
Estimated at
₹ 8,883,793.65
Awarded for
₹ 10,427,705.42
Project highlights
Repairs/Upgradation & Maintenance of Govt. schools in the state of Goa
Contractors
M/s. Sirajuddin Beig
Consultants
M/s. Manoj M. Amshekar