Project Duration
Stipulated Date of Commencement
June 27 2019
Stipulated Date of Completion /
Likely Date of Completion March 07 2020
Likely Date of Completion March 07 2020
Status
100%
Completed
Cost (₹)
Estimated at
₹ 14,198,233.64
Awarded for
₹ 16,599,905.59
Project highlights
Repairs/ Upgradation & Maintenance of schools
Contractors
M/s. Madhurani Enterprises
Consultants
M/s. Nitin Arolkar
See Similar Projects
Upgradation/Renovation of Government College at Quepem, Goa -Civil, Plumbing, Acoustic, Electrical, HVAC and Fire Fighting work.
View Project
Repairs/Upgradation & Maintenance of Government Schools in the State of Goa – Civil, Plumbing,Electrical works – Packge XII- Mormugao Taluka
View Project
Reconstruction of school at GPS Bicholim (Central)- Erection of 200KVA DTC along with the associated H.T UG Cable
View Project