Project Duration
Stipulated Date of Commencement
June 27 2019
Stipulated Date of Completion /
Likely Date of Completion March 07 2020
Likely Date of Completion March 07 2020
Status
100%
Completed
Cost (₹)
Estimated at
₹ 14,198,233.64
Awarded for
₹ 16,599,905.59
Project highlights
Repairs/ Upgradation & Maintenance of schools
Contractors
M/s. Madhurani Enterprises
Consultants
M/s. Nitin Arolkar
See Similar Projects
Repairs/Upgradation and Maintenance of Govt. schools in the state of Goa – Civil, Plumbing and Electrical works-Bicholim Taluka- Package C (G.P.S Gaokarwada Mayem, G.P.S Shirodawadi Mulgao, G.P.S. Haturli Mayem)