Project Duration
Stipulated Date of Commencement
September 12 2018
Stipulated Date of Completion /
Likely Date of Completion July 26 2019
Likely Date of Completion July 26 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 11,756,594.00
Awarded for
₹ 13,018,832.84
Project highlights
Repairs/Upgradation & maintenance of Government Schools
Contractors
M/s. Shree Hari Krishna Constructions
Consultants
M/s. Manoj M. Amshekar
See Similar Projects
Repairs/Upgradation and Maintenance of Government Schools in the State of Goa – Civil, Plumbing, Electrical works – Package VI- (Ponda Taluka)