Project Duration
Stipulated Date of Commencement
November 03 2017
Stipulated Date of Completion /
Likely Date of Completion September 02 2018
Likely Date of Completion September 02 2018
Status
100%
Completed
Cost (₹)
Estimated at
₹ 21,939,320.80
Awarded for
₹ 22953613.12
Project highlights
Repairs/Upgradation & Maintenance of Govt. schools in the state of Goa
Contractors
M/s. Kamar Equipments & Services
Consultants
M/s. Nitin Arolkar