Project Duration
Stipulated Date of Commencement
January 22 2019
Stipulated Date of Completion /
Likely Date of Completion July 21 2019
Likely Date of Completion July 21 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 9,740,455.00
Awarded for
₹ 10,889,310.58
Project highlights
Repairs/Upgradation & Maintenance of Government Schools
Contractors
M/s. Sirajuddin beig
Consultants
M/s. Bhaskar Wagle & Associates