Project Duration
Stipulated Date of Commencement
March 03 2014
Stipulated Date of Completion /
Likely Date of Completion February 09 2014
Likely Date of Completion February 09 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 10,095,133.00
Awarded for
₹ 11,567,161.27
Project highlights
Repairs & Upgradation of Government Higher Secondary Sanquelim
Contractors
M/s. Sirajuddin Beig
Consultants
M/s. Bhaskar Wagle & Associates
See Similar Projects
Civil, Plumbing & Electrical works.
View Project
Repairs/Upgradation & Maintenance of Government Schools In the State of Goa: Package -I (GPS Yeda, GPS Kuskem, GPS Barse, GPS Mahalbadem in Canacona Taluka
View Project
Repairs/Upgradation and maintenance of Government schools in the state of Goa -Package F (GPS Rive, GPS Thane, GPS Shir)
View Project