Project Duration
Stipulated Date of Commencement
November 20 2015
Stipulated Date of Completion /
Likely Date of Completion May 19 2016
Likely Date of Completion May 19 2016
Status
100%
Completed
Cost (₹)
Estimated at
₹ 60,121,594.00
Awarded for
₹ 5,21,44,576.00,
Project highlights
Interior & Furniture works
Contractors
M/s. T.S. Mistry
Consultants
M/s Effective Architectural Services